The Major Projects Management Office: A One Stop Shop for Federal Regulatory Review Processes

From Pipelines to LNG, hydro to nuclear, the Major Projects Management Office (MPMO) is involved in every resource project in Canada that requires a federal environmental assessment. But what is the MPMO, and what do they do? And how, exactly, will they be affected by the new Liberal Government’s plan to make the assessment process more “robust”?

Reporting to the Minister of Natural Resources, the relatively small federal government organization was established in 2007, with a mandate to, “Improve the federal regulatory system so as to have an efficient process, capable of reaching decisions on major resource projects in a more timely and effective manner, while ensuring careful consideration of environmental standards, Aboriginal consultation obligations and technical requirements.”

In practice, the MPMO operates as a single point of contact for projects that are navigating the winding pathways of federal environmental assessment and regulatory permitting, required for any major resource project in Canada to proceed.

This means that companies can come to the MPMO before they submit a project description that would set an environmental assessment in motion, and have their questions about the process answered.

Whether or not a company approaches the office, though, the MPMO will be involved in the environmental assessment and permitting process. When a company approaches the environmental assessment agency, or another department, with a project description, the MPMO becomes involved right away, facilitating collaboration between the various federal departments that will be involved in the regulatory process for the project.

Out of this collaboration, the MPMO then creates a Project Agreement, outlining the roles and responsibilities within the federal government, and setting out timelines for the various stages of the process. Once the project agreement is complete, deputy ministers sign it, and the MPMO puts it up on their website. Making the Project Agreements public in this way ensures that the process is transparent, and holds the government accountable to the various stakeholders in the project; companies, first nations and other interested parties can see exactly how the regulatory review is going to unfold.

With the Project Agreement signed and made public, and the regulatory review underway, the MPMO shifts into monitoring mode: tracking the review’s progress, and watching for any issues that might arise. If and when there are issues, the MPMO’s job is to resolve them, to keep things on track, and ensure that the review is both efficient and effective.

The MPMO does a lot of things, but there are a few things it doesn’t do; the office’s role is, first and foremost, to coordinate between federal departments. It does not, itself, play a part in the decision-making aspect of the review process, leaving the environmental assessment and regulatory permitting entirely in the hands of the relevant departments.

With the new Liberal Government in charge, and James Carr newly at the helm of the Ministry of Natural Resources, however, this process, and the MPMO’s role in it, may change.

Prime Minister Trudeau’s mandate letter to Carr emphasizes a focus on clean energy, and a commitment to restoring the public’s faith in the environmental review process. Carr has said that there will be a transition to an amended project evaluation process, but has not given any details as to what or when that might be.

In a talk he gave recently at an International Energy Agency meeting in Paris, Carr said that the ministry will find a “sweet spot” between addressing the concerns of oil and gas stakeholders and furthering the Liberal environmental mandate.

For everything that’s been said so far, it’s still very early in the game, and nobody at the MPMO, or at any other agency, is quite sure how the mandate will affect oil and gas, and other natural resource sectors.

But for now, Carr says that it will be business as usual for projects currently undergoing an environmental and regulatory permitting review.

Preparing For The Worst

Experts Weigh In On Emergency Preparedness Measures Every Business Should Consider

  • Response Procedures During & After An Emergency
  • Know Your Contacts & Inform Your Staff
  • Preparing For the Worst to Ensure the Best Outcome

Explore Posts By Category

Facebook Feed

Congratulations Ho Chu! Winner of this year's M1 driver draw at the Global Petroleum Show. ... See MoreSee Less

2 weeks ago

View on Facebook

Trinity Power Rentals added 8 new photos to the album: ECABC Annual Golf Tournament 2017 — at Surrey Golf Club.

Trinity Power was at hole 12 for the ECABC golf tournament again this year. Frosty beverages were given and a draw for a beautiful Scotty Cameron putter took place. Thank you ECABC for hosting this awesome annual event.
... See MoreSee Less

4 weeks ago

Trinity Power was at hole 12 for the ECABC golf tournament again this year. Frosty beverages were given and a draw for a beautiful Scotty Cameron putter took place. Thank you ECABC for hosting this awesome annual event.

Konrad Sander, Nick Foster and 9 others like this

Deb Cahill-TraffordGreat day, thank you for your support!

4 weeks ago
Avatar

Comment on Facebook

Newsletter

Join Trinity Power’s Monthly Newsletter

By checking this box you are giving Trinity Power Rentals express consent to send you commercial electronic messages. This includes:
  • > Relevant & Insightful Articles
  • > Equipment Line News & Videos
  • > Industry News & Reports
  • > Promotional Type Email
I consent

Most Popular Articles

  • Fuel Delivery System Construction Underway For YVR read more >
  • 4 Ways to Reduce Your Global Adjustment Costs read more >
  • Case Study: A Generator-Free Film Set read more >
From the Blog
Trinity Power & R.Stahl Partner to Rent Explosion Proof Equipment

Trinity Power Partners With R. STAHL to Provide Explosion Proof Temporary Power Equipment

Trinity Power is pleased to announce that we have partnered with R. STAHL, the world’s foremost innovator in explosion proof and explosion protected components and systems, to represent their TEMPEX explosion proof temporary power system in Weste...

An Emergency Power Checklist for Business

Is Your Business Prepared For a Power Outage?

Spring has arrived and, with it, unpredictable weather and the power outages that often follow. As recently as April 7th, a snow and wind storm caused a major outage in Ontario that affected 45,000 residents. Meanwhile, the spring melt in BC is see...

Gas Plant Case Study

Trinity Goes the Distance To Power A Gas Plant Project

What does it take to deliver a bid-winning temporary power solution? In the case of our recent project at a phase III gas plant, the answer is: 2 designs, 5 vendors including Trinity Power, and 8 equipment locations spread across North America. ...

NEED POWER?
WE CAN HELP
CALL US NOW:
1-888-PLUG-N-GO
TOLL FREE
1-888-758-4646