Critical Steps To Plan For In Plant Turnarounds

Temporary Power Rentals

If you have previously participated in a scheduled plant shutdown, either as a manager, engineer, QA specialist or as part of the maintenance team, you know how overwhelming, chaotic and difficult to manage this short, but intensive period might be. Whether it is required by industry regulations or planned as part of the plant maintenance schedule, the annual plant shutdown must be as efficient as possible in terms of costs, work and time to minimize the inevitable financial losses that come with it. Careful and consistent planning is essential to the plant turnaround (the plant’s shutdown management process).

To best optimize a plant turnaround, you should allow 3 to 18 months of data collection, analysis and effective allocation of responsibilities, depending on the plant’s size. There are several critical stages in planning for a plant shutdown, each of which is key to sticking to the shutdown timeframe, avoiding additional losses and lowering the impact on the business as a whole.

  • Timing: Picking the right time for a plant shutdown is the responsibility of the owner or the senior management team and depends on factors such as the nature of business, time of year and availability of manpower, resources and contractors in the area. Scheduling a shutdown in the hottest and coldest months has serious safety and efficiency implications and should be avoided. Keep in mind that while a plant shutdown cannot be skipped altogether, it can be performed less frequently, depending on the results of previous ones and the industry you operate in.
  • Selecting turnaround team members: Since a scheduled shutdown affects all levels of a business, the turnaround team should include specially trained staff from all areas of responsibility, including administration, operations, accounting, QA, maintenance, etc. Selecting a supervisor, who has enough knowledge and experience to manage the team and optimize the turnaround process, is among the most crucial decisions involved in the planning stage.
  • Creating a work list: The work list details the various procedures and specific tasks that should be executed during the shutdown, as well as outlines the responsibilities of each team member, and sets the process timeframe. This is perhaps the blueprint, upon which all following decisions are based, so it should be prepared with care and deep understanding of the process. At this point, any pre-shutdown work necessary needs to be identified and scheduled.
  • Materials and contractors: Long delivery items and equipment that will be used during the shutdown should be ordered well in advance and all other necessary materials should be procured. This is the right time to contact any contractors that will be involved in the process and set up contracts and terms. Keep in mind that some materials, services or equipment may be in higher demand during certain times of the year, so planning ahead is again critical.
  • Process optimization: Finally, the turnaround team manager, with the help of the engineering team, should go over the entire task list and figure out ways to improve resource use, cut down on time and costs and finalize the work schedule.

Remember that unscheduled shutdowns may cost up to ten times more than carefully planned and executed ones, which are your stable insurance policy against catastrophic failure.

Get Prepared

Call Toll Free 1-888-758-4646 to speak with a power specialist about the next step in becoming emergency prepared.

OR

Submit this form and a Trinity Power specialist will arrange an appointment to discuss further.

Explore Posts By Category

Facebook Feed

Trinity Power Rentals shared NHL Trash Talkers's photo.

LET’S GO OILERS!
... See MoreSee Less

Game 2 Oilers vs Ducks goes tonight The Oil are up 1-0 in the series. Will they make it 2-0? #GrandLarssony

24 hours ago

View on Facebook

Kurt with Lianne Ransom, winner of our little draw at Minerals North 2017... congrats Lianne! ... See MoreSee Less

2 days ago

View on Facebook

Newsletter

Join Trinity Power’s Monthly Newsletter

By checking this box you are giving Trinity Power Rentals express consent to send you commercial electronic messages. This includes:
  • > Relevant & Insightful Articles
  • > Equipment Line News & Videos
  • > Industry News & Reports
  • > Promotional Type Email
I consent

Most Popular Articles

  • 4 Ways to Reduce Your Global Adjustment Costs read more >
  • Case Study: A Generator-Free Film Set read more >
  • Trinity Power and Litespan Electrical Inc Provide Quick Solution to Power Emergency read more >
From the Blog
An Emergency Power Checklist for Business

Is Your Business Prepared For a Power Outage?

Spring has arrived and, with it, unpredictable weather and the power outages that often follow. As recently as April 7th, a snow and wind storm caused a major outage in Ontario that affected 45,000 residents. Meanwhile, the spring melt in BC is see...

Gas Plant Case Study

Trinity Goes the Distance To Power A Gas Plant Project

What does it take to deliver a bid-winning temporary power solution? In the case of our recent project at a phase III gas plant, the answer is: 2 designs, 5 vendors including Trinity Power, and 8 equipment locations spread across North America. ...

YVR Jet Fuel Delivery Solution

Fuel Delivery System Construction Underway For YVR

With over 20,000 runway movements and 1.6 million passengers coming and going in February alone, the Vancouver International Airport sees a lot of air traffic. Fueling that air traffic is no small feat. Currently, fuel arrives at the airport b...

NEED POWER?
WE CAN HELP
CALL US NOW:
1-888-PLUG-N-GO
TOLL FREE
1-888-758-4646